Critical Timeline Projects

Another example of a contract we worked on with penalties and performances bonuses was the Second Narrows Bridge rehabilitation project.

  1. The contractor will be awarded a $25,000 per day bonus for each 24 hour period, prior to 5:00 am August 11, 1996, that Deck Work is complete and the entire 6 lanes of the bridge are unencumbered to traffic.
  2. For each 24 hour period, or part therof, following 5:00 am August 16, 1996, that Deck Work is not complete the Contractor will be assessed a penalty of $100,000.